What validation ready handover actually includes

A builder hands over at practical completion. A regulated facility cannot be used until it has been qualified. Those two events are weeks or months apart, and the contract usually says nothing about the space between them.

Home › Technical notes › Validation ready handover

The gap nobody prices

Practical completion means the works are complete enough for the client to occupy. In ordinary commercial construction that is the end of the story.

In a regulated facility it is the beginning of a second process. Your validation team, or a third party, now has to demonstrate that the facility does what it was specified to do. Installation qualification, operational qualification, performance qualification, classification testing to ISO 14644, and whatever else your quality system requires.

Every one of those steps needs evidence from the construction phase. If that evidence was not assembled as the work happened, somebody has to reconstruct it after the builder has demobilised, from a contractor who has already been paid and moved to the next job.

The cost of that reconstruction is never in anyone's budget, and it is nearly always paid by the client in delay.

What should be in the handover

Construction and compliance evidence

  • The certificates your certifier required for occupation, complete and in one place
  • Material and product certification for the finishes, panels and sealants actually installed, not the ones originally specified
  • Penetration and passive fire records, with locations
  • As built drawings that reflect what is behind the wall, including services that moved during construction

Mechanical services evidence

  • Commissioning records for the air handling system, with the as commissioned figures
  • Air flow, air change rate and pressure differential readings, room by room
  • Filter certification, including the installed location of each filter
  • Controls setup and the setpoints as left
  • Any balancing report the mechanical contractor produced

Room fabric evidence

  • Confirmation of the finish schedule as installed
  • Sealant types and locations where they matter to cleanability
  • Door and pass through schedules with hardware as fitted

Operation and maintenance

  • Manuals for every installed system, with the model actually installed
  • Spare filter sizes and part numbers, because the first filter change should not be an investigation
  • Warranty documentation with start dates

What to write into the contract

Three things, and they cost nothing to include at the start.

  1. Define the handover deliverable in the scope, as a schedule of documents rather than a phrase. "Validation ready" means whatever the contract says it means.
  2. Tie a payment to it. A meaningful proportion of the final claim released on the documentation, not on the physical works. This single clause changes the behaviour of every contractor on the job.
  3. Require the evidence progressively. Monthly, as the work proceeds. Assembling it at the end is how it goes missing.

What a builder cannot do

We are not a validation service and we should not be. Qualification is performed by your validation team or an independent party, and your quality system owns it. A builder who offers to validate their own work has a conflict you do not want.

What a builder can do is build the facility so it will pass, and hand over the evidence the people doing the qualification need. That is the whole job.