A builder hands over at practical completion. A regulated facility cannot be used until it has been qualified. Those two events are weeks or months apart, and the contract usually says nothing about the space between them.
Practical completion means the works are complete enough for the client to occupy. In ordinary commercial construction that is the end of the story.
In a regulated facility it is the beginning of a second process. Your validation team, or a third party, now has to demonstrate that the facility does what it was specified to do. Installation qualification, operational qualification, performance qualification, classification testing to ISO 14644, and whatever else your quality system requires.
Every one of those steps needs evidence from the construction phase. If that evidence was not assembled as the work happened, somebody has to reconstruct it after the builder has demobilised, from a contractor who has already been paid and moved to the next job.
The cost of that reconstruction is never in anyone's budget, and it is nearly always paid by the client in delay.
Three things, and they cost nothing to include at the start.
We are not a validation service and we should not be. Qualification is performed by your validation team or an independent party, and your quality system owns it. A builder who offers to validate their own work has a conflict you do not want.
What a builder can do is build the facility so it will pass, and hand over the evidence the people doing the qualification need. That is the whole job.
Talk it through with a licensed builder who has delivered GMP compliant rooms, before the design is locked. That is the point where the decisions are cheapest to change.