Case study

GMP cleanroom facility, Queensland

A classified manufacturing facility for a regulated manufacturer, delivered as a single contract covering the base building, the structure, the services and the cleanroom fitout, through to a handover the client could validate against.

Home › Projects › GMP cleanroom facility, Queensland
Sector
Regulated manufacturing
Location
Queensland
Building class
NCC Class 8
Delivery
Base build to validation ready handover

The brief

A classified manufacturing facility, built new, with the cleanroom envelope, the mechanical services and the base building all delivered by one contractor. The client wanted a single accountable party, because their previous experience had been a fitout specialist working inside somebody else's shell with the gaps between the two contracts left for the client to manage.

What made it a builder's job, not a fitout job

Most of the difficulty on this project sat outside the cleanroom envelope.

  • The structure had to carry the services and the ceiling system, and the ceiling system had to be coordinated with the fire services before anything was set out
  • The use required a Class 8 classification, which brought building code obligations that a fitout contract would not have touched
  • Town planning approval was required before building approval could proceed, which put a statutory process on the critical path
  • Two separate Performance Solutions were needed under the National Construction Code before the certifier could issue approval

None of that is cleanroom work. All of it had to be resolved before the cleanroom work could start, and a panel contractor is not in a position to resolve any of it.

The two Performance Solutions

Two aspects of the design could not comply with the deemed to satisfy provisions of the National Construction Code, which is common in facilities of this type because the code's default assumptions do not fit a classified manufacturing layout.

Fire and egress

A fire engineer was engaged to develop a Performance Solution covering exit travel distance, where the layout required a distance greater than the deemed to satisfy provision allows, and the distance between alternative exits. The fire engineering report was assessed by the certifier as part of the building approval.

Access

An access consultant developed a Performance Solution addressing the application of the access provisions to the facility, taking into account the nature of a Class 8 facility and the controlled entry requirements of the classified areas.

Both of these were identified during design, not during construction. That is the difference between a consultant fee and a program delay. A Performance Solution discovered after the slab is poured is a very different conversation.

Coordinating the trades

The trade packages on a facility like this extend well past the cleanroom contractor. This project brought together the cleanroom panel contractor, mechanical services, electrical, hydraulic, wet fire, fire detection, passive fire, specialist doors, structural steel fabrication, flooring, glazing and concreting, each with an interface into the cleanroom envelope.

The interfaces are where these projects fail. The ceiling suspension system and the sprinkler layout occupy the same space. The panel penetrations and the electrical rough in happen in the same week. The floor finish cannot start until the wall system is up, and the wall system cannot start until the slab is right.

We ran design stage meetings with the consultants and the key trades together, before construction, to find those clashes on paper.

Handover

The facility was handed over with the construction evidence assembled as the work proceeded: the certificates the certifier required, the commissioning records for the mechanical services, and the documentation the client's validation team needed to begin qualification without waiting on us.

The client subsequently engaged us for a second facility.

Published without the client's name, site or identifying project detail. Referees and further detail are available directly under a confidentiality undertaking.