Technical note

Why cleanroom programs slip

In our experience cleanroom projects do not usually slip because the building work was slow. They slip because of decisions and orders that should have happened months earlier, and the construction program simply reveals it.

Home › Technical notes › Why cleanroom programs slip

One: long lead items ordered late

A classified facility depends on items that are not held in stock anywhere in Australia and are often built to order overseas.

  • Air handling units built to the facility's specification
  • Specialist cleanroom doors and interlocks
  • Pass through hatches, particularly interlocked or purged types
  • Biological safety cabinets, isolators and laminar flow units
  • Autoclaves and washers, especially double door types built into the wall
  • Building management and environmental monitoring hardware

Each of these has a lead time that can run into months, and several of them cannot be ordered until a design decision is final. The critical path usually runs through an order, not through a trade.

The first thing to do with a cleanroom program is not to sequence the trades. It is to list the long lead items, work backwards to the date each has to be ordered, and then work backwards again to the decision that has to be made before it can be ordered.

Two: approvals started too late

Classified facilities frequently need more than a building approval.

  • A town planning approval where the use, the intensity or the built form changes, which is a statutory process with its own timeframes and no way to compress it
  • Performance Solutions under the National Construction Code, which need a consultant, a report and assessment by the certifier
  • Regulator engagement where the facility type requires it
  • Utility authority approvals for supply upgrades, which are routinely underestimated

None of these are difficult. All of them take calendar time that cannot be bought back, and all of them can start earlier than they usually do.

Three: design decisions left open

A cleanroom design has a small number of decisions that everything else waits on. Classification and layout. Pressure regime. Equipment schedule. Plant location. While any of those is open, drawings cannot be finalised, orders cannot be placed and trades cannot be engaged with confidence.

Projects lose months to a design that is ninety percent settled, because the remaining ten percent is holding the orders.

Four: equipment access discovered late

Large equipment has to physically get into the room. If that was not designed, the answer involves a temporary opening, a crane, a revised sequence, and a delay while everyone works out who pays.

Five: handover never defined

The works finish, and then the project sits while documentation is assembled, commissioning figures are chased and the validation team waits. This is entirely avoidable and it is covered in our note on validation ready handover.

What a realistic program looks like

One that is built backwards from the date the facility has to be operational, through qualification, through handover, through commissioning, through construction, through the long lead orders, to the design decisions those orders depend on. Most programs are built forwards from the start date, which is why the compression always lands on construction.